[Xrayops] Updated estimated for refill of the Storage Ring
APS Experiment Hall X-ray Operations Problem List
xrayops at mailman.aps.anl.gov
Thu Dec 18 10:22:48 CST 2008
The repair of the motorized fused disconnect for the Booster RF system
is well underway and will most likely finish within the next hour or so.
Once that repair has finished, the RF Group will need to verify that the
original problem causing the Mod Anode voltage drop in that RF system
was successfully repaired yesterday.
Based on this information, we estimate the refill of the SR will take
place at approximately 13:00. A PA announcement will be made at least
1/2 hour before the refill.
We will send out further e-mail updates as more information becomes
available.
Karen Schroeder
More information about the XRAYOPS
mailing list