[Xrayops] IK4:PS investigation update
APS Experiment Hall X-ray Operations Problem List
xrayops at mailman.aps.anl.gov
Sat Jun 28 11:38:15 CDT 2008
Personnel from the PS Group are onsite and have started replacing a transformer
for the S:IK4:PS. Once this work is complete and the PS has been warmed up, a
fill on fill will be performed immediately. As much notice as possible will be
provided via the message board, audible announcement, and this email address.
ASD Operations Group
Main Control Room
(630) 252-9424