[Xrayops] Shutter Permit to be removed for ongoing IK4 investigation
APS Experiment Hall X-ray Operations Problem List
xrayops at mailman.aps.anl.gov
Sat Jun 28 14:53:49 CDT 2008
Due to ongoing issues with S:IK4:PS, the PS Group are connecting
additional diagnostics to the PS. When they are ready, a 15 minute
warning announcement will be given, and then Shutter Permit will be
removed in order to allow continuous pulsing of the Kickers with stored
beam. This will greatly improve the ability of the PS Group to identify
and correct the problem with the PS.