[Xrayops] APS Additional User Operations
APS Experiment Hall X-ray Operations Problem List
xrayops at mailman.aps.anl.gov
Fri Mar 28 13:07:17 CDT 2008
Additional User Operations Tuesday, 8:00 AM April 1, 2008
to 8:00 AM April 2, 2008
To help APS users affected by the loss of user beamtime earlier
this week, APS Management has decided to continue the current
weeks run through the maintenance period scheduled for April 1-2, 2008.
Therefore, user beam will be available during the scheduled
Studies/Maintenance period from 8:00 AM Tuesday, April 1, 2008
to 8:00 AM Wednesday, April 2, 2008
Further changes or additions to the operations schedule will be
discussed at the Monday Operations Meeting and communicated to
the APS community as soon as possible.
--
John Quintana
Associate Division Director
Mechanical and Interlock Systems
APS Engineering Support Division
Argonne National Laboratory
9700 South Cass Avenue, Bldg 401
Argonne, Illinois 60439
(630) 252-6716(ph) (630)252-7187(fax)