[Xrayops] 2ND UPDATE: top-up aborted

APS Experiment Hall X-ray Operations Problem List xrayops at mailman.aps.anl.gov
Fri Aug 2 00:35:56 CDT 2013


Re: On Thursday August 1st, 2013 at 21:44 top-up was aborted due to a PAR power supply communications issue.

2ND UPDATE: power supply technicians are onsite; current estimated time for repairs is 1 hour


More information about the XRAYOPS mailing list