[Xrayops] Update

APS Experiment Hall X-ray Operations Problem List xrayops at aps.anl.gov
Sat Nov 21 03:38:51 CST 2015


Power Supply technicians have arrived and are beginning the repair of the Booster power supply. Estimated time of completion ~1.5hrs.

-Ops