[Xrayops] APS Status Operator Message Update

APS Experiment Hall X-ray Operations Problem List xrayops at aps.anl.gov
Thu Feb 6 19:09:22 CST 2025


Problem: Beam lost due to power issues in bldg 420.
Activity: AFD investigating bldg 420, no access to building allowed. FAC investigating power issues in bldg 420.
Estimated time of shutter enable: 22:00
Next planned update: 20:00