[Xrayops] update on Fill #1 loss at 23:49 on 6/2/10

APS Experiment Hall X-ray Operations Problem List xrayops at mailman.aps.anl.gov
Thu Jun 3 03:21:19 CDT 2010


02:50 - The AES-SI group personnel cycled the 31-ID SS2 shutter at the 
beamline. All FEEPS and PSS faults at 31-ID have been cleared. We 
disabled the shutter permit key for S1-35 and preparing to inject.

03:05 - Fill #2 was delivered.